Stages of SIPS Panel Construction - Week 5
Work started to flow a little quicker this week with the completion of the front wall. At 150' in length and 24' tall, it's quite a structure. This week's photos will show the last few trusses being placed with a skytrack. Once trusses are completed, we can really focus both crews on setting the final roof panels. About 40% of the roof is completed to date.
Our goal is to have all of the wall & roof panels in place by end of the day Thursday May 18th. From there, we'll have to complete the panel shades along the north & west walls and the interior truss bracing. We are in the final stages of the project coming into the week.